After you have reviewed and approved all content, schedule the batch. The Schedule Update button will not be active unless you have reviewed all the pages in the batch.
Schedule the Maintenance Update
1. Select Schedule Update.
2. Click the calendar to select a date for the update.
3. Click Schedule.
4. The maintenance table will populate, and the batch will display as Scheduled with the corresponding Release Date.
Once your update is scheduled, you can leave the page and do other things. The status will change to Published when the update is complete on the production server.